USCG Bridge Permit Amendment Issuance

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Gary Kassof
Project: 
Bayonne Bridge Raising
Type: 
Ad Hoc Activity
This permit is required for new construction, reconstruction or modification of a bridge or causeway over waters of the United States. Federal law prohibits the construction of any bridge across navigable waters of the United States unless first authorized by the Coast Guard. The Coast Guard approves the location and clearances of bridges through the issuance of bridge permits or permit amendments for new construction.<br />

Milestones

Milestone Target Actual
Milestone Start - USCG Bridge Permit Amendment Issuance 03/14/2012 03/14/2012
Milestone End - USCG Bridge Permit Amendment Issuance 05/23/2013 05/22/2013