MOU for I-70

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Jeanette Mar
Environmental Program Manager for FHWA - DelMar Division, Maryland Office
Project: 
Baltimore Red Line
Type: 
Ad Hoc Activity
Coordinate with FHWA and MDOT, including the development of a Memorandum of Understanding concerning the use of I-70 right-of-way.

Milestones

Milestone Target Actual
Milestone Start - MOU for I-70 06/28/2012 06/28/2012
Milestone End - MOU for I-70 07/30/2012 06/28/2012