Complete Section 106 Programmatic Agreement

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Mr. J. Rodney Little
Maryland State Historic Preservation Officer
Project: 
Baltimore Red Line
Type: 
Ad Hoc Activity
Section 106 of the National Historic Preservation Act mandates federal agencies undergo a review process for all federally-funded and permitted projects that will impact sites listed on, or eligible for listing on, the National Register of Historic Places. Specifically it requires the federal agency to "take into account" the effect a project may have on historic properties. It allows interested parties an opportunity to comment on the potential impact projects may have on significant archaeological or historic sites. The main purpose for the establishment of the Section 106 review process is to minimize potential harm and damage to historic properties.<br /><br />This action will be completed in coordination and consultation with the Maryland Historical Trust.

Milestones

Milestone Target Actual
Milestone Start - Complete Section 106 Programmatic Agreement 11/29/2012 11/29/2012
Milestone End - Complete Section 106 Programmatic Agreement 02/27/2013 02/25/2013