Gordon Butte Pumped Storage

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
COMPLETE
COMPLETION DATE
Dec 14 2016
2 OUT OF 2
ENVIRONMENTAL REVIEW
AND PERMITTING PROCESSES COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Description: 

Gordon Butte Pumped Storage (Project No. 13642) is a proposal to construct an original, closed-loop pumped storage project that would provide 400 MW of generation capacity in Montana.  The proposed project would consist of, among other facilities, an upper and lower reservoir each with an active storage of 4,070 acre-feet, a penstock, a powerhouse, two substations, and a 5.7 mile-long, 230-kilovolt transmission line.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed. 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.

To view Timetable chart, please turn device sideways (landscape)

Overall Project Timetable
STATUS
Schedule
Extension
Ahead of Schedule
Paused

Action Information

For additional information, please select an Action from the Permitting Timetable above.

Action:
Responsible Agency:
Bureau:
Action Status:
SHPO:
Action Identifier:
Action Outcome:
Milestone
Original Target Date
Current Target Date
Milestone Complete